Hut 8 raises buyback to $1B as Beacon Point fully leased

Hut 8 says Beacon Point is fully commercialized after a second 352 MW IT lease, and lifted its share buyback authorization to $1 billion.

·
Hut 8 raises buyback to $1B as Beacon Point fully leased

Hut 8 said Beacon Point became fully commercialized during the third quarter of 2026, after the company signed a second IT lease of 352 MW. In the same update, the company said it raised its buyback authorization to $1 billion, according to an SEC exhibit it filed.

Beacon Point fully commercialized

The SEC exhibit states that Beacon Point reached full commercialization in the third quarter of 2026. The step that completed it was a second lease for 352 MW of IT capacity.

Hut 8 also gave delivery targets for two sites. The company said the first data-hall delivery at River Bend is targeted for Q2 2027, and that Beacon Point Phase 1 is targeted for Q3 2027. These are Hut 8's own timing targets, not completed milestones, and they could move as construction proceeds.

A 7,859 MW pipeline and a larger buyback

Hut 8 said its development pipeline stands at 7,859 MW, with 1,330 MW of that under construction. The gap between the two figures shows how much of the pipeline has yet to move into active building.

On capital returns, Hut 8 said it had used its full original $250 million program. It repurchased 953,802 shares for $74.7 million during the quarter and 2,384,677 more for $175.3 million after quarter-end, funded by selling about 954 and 2,148 bitcoin, for 3,338,479 shares in all. On November 2, its board approved another $750 million, lifting the total authorization to $1 billion.

Taken together, the leasing, the build schedule and the larger buyback authorization show the company pairing data-center expansion with a bigger commitment to returning capital. The lease on Beacon Point and the 1,330 MW under construction are the concrete items tied to delivery dates.

The update arrives as other crypto-linked businesses report infrastructure and product moves.

What this suggests is a company moving a large share of its planned capacity toward leased, contracted use while keeping a sizeable repurchase program available. Whether the River Bend and Beacon Point targets hold will become clearer as the Q2 2027 and Q3 2027 dates approach.

Correction (Nov 17, 2026): Was: The first version said the filing did not say how much of the share repurchase program had been used. Now: The filing says Hut 8 used the full original $250 million program, buying back 3,338,479 shares funded by bitcoin sales, before its board raised the total authorization to $1 billion on November 2. Corrections log

How we verified Checked against the document (Hut 8 8-K EX-99.1, 4 Nov 2026).

Sources

Checked by OnchainBeat · 1 link, 1 primary document
  1. DocumentHut 8 8-K EX-99.1, 4 Nov 2026sec.gov